Page 78 - Industrial Plant 2020
P. 78
Special convoy (19 trucks) and trailors Internal view of one deluge valve container for
Russia
approved vendors of the suppliers of instruments
that had to be installed with packages
• identification and choice of special construction
materials and alloys that can withstand extreme
cold or extreme warm environments, suitable for
enclosures/containers (cooling systems for hot
environment and heating systems for very low
temperatures)
• special welding processes done by qualified
welders and with special tests such as penetrant
CO systems for Russia (more than 1400 cylinders) liquids, X-rays, even in presence of external
2
inspectors also during construction process
• assembling with internal final acceptance tests
even before visit of EPC’s inspectors
• finishing and painting with several cycles, specific
painting processes and special thickness
• shipment with suitable logistic means, also special
cargo because almost packages reached 30 tons
weight each.
• meeting delivery times at site
SANCO has managed voluminous and complex
projects but some have turned out to be more
Deluge valves on skid for Russia remarkable than others.
In particular, it is worth to mention three totally different
cases with very extreme temperatures (-52°C projects located respectively in Russia, Kazakhstan
+65°C) and Kuwait.
• improving the performances of the fire-fighting
systems and equipment accordingly SANCO has managed
• granting the agreed delivery schedules and sizeable and complex projects
warranties, tailored to meet client’s construction in very diverse environments,
needs. e.g. in Russia, Kazakhstan
and Kuwait
As a result, SANCO has been working and challenging
for: The projects have been carried out throughout two
• accurate selection among the end user’s years by three different project task forces.
IndustrIal Plants - May 2020