Page 35 - Industrial Plant 2020
P. 35

Picture 7


















            Pictures 8a, b, c - beam no. 7

















            Picture 9                                 Picture 10

            by oblique cuts to allow them a rotation towards the
            outside and make the lowering by crane  easier.
            In the same way the pile no. 4 (end of May), the pile
            no. 7 (first half of June), the pile no. 6 (first week of
            July), the pile no. 3 (end of July) and the pile no. 8
            (early days of August), were dismantled and the
            sections taken away by Fagioli SPMTs (pictures 14a,
            b, c).
            After the demolitions of these piles, the Berger beam   Picture 11
            no. 11 (weighing 750 ton each) was cut and lowered
            with the strand jacking system be the end of May
            (pictures 15, 16, 17).
            The demolition of V shape piles no. 10 and no. 11 pile
            was  executed with an operation of controlled
            explosion by the end of June, out of Fagioli scope of
            work (picture 18).
            Pile no. 8,  being 4 meters longer than all the others,
            required some additional cuts. Pile no. 2, the last one
            left, was demolished at the same time as the pile 8.
            The  demolition  of  the  bridge  ended  on  the  12th  of
                                                  st
            August 2019 (Fagioli scope of work ended on the 31
            of July).                                 Picture 12

                                                                                    IndustrIal Plants - May 2020