Page 38 - Industrial Plant 2020
P. 38
Picture 23
loads imposed on the hydraulic system from the remaining “V” shape piles, were lowered by Fagioli
concrete structure equal to 2400 tons per tower pair. In strand jacking system and Fagioli cantilever beam
order to increase precision and constantly monitor the which was designed to distribute the loads onto the
load transmitted to the reinforced concrete structure a pile in an isostatic and uniform manner, able to
reading system with Fagioli load cells was also adopted, perfectly transfer the 250 ton load of each of the 2
with an accuracy of 0.5%, with readings H24, 7 days a strand jacks onto the No. 3 beams of the pile. It is
week. The system was mounted at the base of each worth pointing out that each of the auxiliary metal
jack. The securing activity of the piles allowed the structural element was designed in such a way that the
lowering and removal operation of Berger beam 11 load transferred to each concrete structure, was
(760 ton). Picture 24 applied “by support”, that is by contact, and not “by
A specific and deep analysis of the eventual traction”. The Berger beam before the lowering
deformations of the berger beams during lowering operation, was cut and lifted, in order to allow the
operation was constantly carried out. The berger removal of the structure which supported the road
Picture 24 beams on the Western side, supported by the surface (drawing in picture 25)
The lifting of the Berger beam was carried out by
means of a metal structural beam which supported the
floor from below, by contact. (Picture 26)
This action increased safety
on site
For what concerns the disassembly of the piles, this
activity was carried out by making longitudinal cuts in
the concrete structure, about 36 m long with thickness
up to 3 m. The whole concrete structure was divided
into no.3 large blocks with a weight suitable for lifting
by means of two Fagioli Demag CC-2800 crawler
cranes, in SSL configuration, with 78m boom, Superlift
300 ton at 13m (See picture 27)
The rigging system, consisting of two hooks and wire
ropes on the hook, was designed in such a way that
the concrete structure was supported from below, in
strategic positions, so that the bending moment in the
IndustrIal Plants - May 2020
36

