Page 37 - Industrial Plant 2020
P. 37

Pictures 20a, 20b























            Pictures 21, 22 - Balance system on Berger beam No. 8



            take place in conditions of maximum safety and   The external vertical load, equal to about 300 tons,
            stability.                                was applied by means of two Fagioli Strand Jacks
                                                      positioned onto the cantilever beam of the pile,
                                                      contrasted at the base by a counterweight of adequate
            Analysis of the structure, tests          mass, in order to satisfy the balance verification. The
            and engineering solutions                 load of each strand jack was distributed in an isostatic
                                                      way on no. 2 beams by means of a metal carpentry
            In order to identify the conditions of post-incidental   structure (pictures 21 and 22)
            stress and the residual resistant capacities, the entire   Another example of re-balancing load is the one
            work was modeled on the finished elements and   applied to the cantilever bridge sections of the large
            calculated in all its temporal phases from construction   Eastern piles no. 10 and no. 11.  No. 3 pairs of Fagioli
            to collapse up to the representation of all the   lifting towers equipped with strand jacks were erected,
            intermediate steps of the planned dismantling   two for pile 10 and one for pile 11, each 50 m high,
            operations. Detailed studies were executed, with a   positioned  onto  concrete foundations.  The  lifting
            comparison with the available data of the original   towers, had the function of temporarily supporting the
            project.                                  three cantilever beams of the piles from below, in the
            Fagioli proceeded with repeated load tests, carried out   event of structural collapse of the stays (See picture
            by detecting the deformations of the structure at the   23).
            passage of remote controlled heavy vehicles (SPMT),   The lifting towers, had the function of temporarily
            simulating the future loads to which the structures   supporting the three cantilever beams of the piles from
            would have been stressed during the dismantling   below, in the event of structural collapse of the stays.
            phases. (Pictures 20a, 20b)               The support beams also applied a vertical load
            One of the most crucial aspect was the dismantling of   upwards of about 600 tons to ensure a re-balancing of
            the berger beam no. 8 (the first one), due to its   the  loads.  The lattice lifting towers and  beams  were
            unbalanced  condition  created  by  the  loss  of  the   therefore designed for two load combinations: the first
            adjacent beam and pile.                   called “service”, with loads imposed by the hydraulic
            The re-balancing operation was executed by applying   system on the concrete structure equal to 600 tons per
            external forces at the support of the collapsed pad.   pair of towers and the second called “extra-heavy” with